WORK SEQUENCE

The project’s construction will occur in eight phases

Phase 1

  • Construct center portion of Minnesota Avenue improvements, including utilities, storm drain work, and pavement, between southern limit of work and Nannie Helen Burroughs Avenue

Phase 2

  • Construct the western portion of Minnesota Avenue roadway up to curb, between southern limit of work and Nannie Helen Burroughs Avenue, including storm drainage and utility work.

 

  • Construct new sidewalk and streetscape along SB Minnesota Avenue between southern limit of work and Nannie Helen Burroughs Avenue.

Phase 3

  • Construct completion of intersection work in Minnesota Avenue median at intersections with Benning Road, Metro Station Bus Lot, and Nannie Helen Burroughs Avenue

Phase 4

  • Construct the eastern portion of Minnesota Avenue roadway up to curb, between southern limit of work and Nannie Helen Burroughs Avenue, including storm drainage and utility work

 

  • Construct new sidewalk and streetscape along NB Minnesota Avenue between southern limit of work and Nannie Helen Burroughs Avenue

Phase 5

  • Construct Minnesota Avenue southbound roadway from Nannie Helen Burroughs Avenue to the northern limit of work, and Nannie Helen Burroughs westbound lanes in the intersection area

Phase 6

  • Construct Minnesota Avenue center roadway from Nannie Helen Burroughs Avenue to the northern limit of work, and Nannie Helen Burroughs westbound lanes in the intersection area

Phase 7

  • Construct Minnesota Avenue northbound roadway from Nannie Helen Burroughs Avenue to the northern limit of work, and Nannie Helen Burroughs westbound lanes in the intersection area

Phase 8

  • Construct raised median construction on Minnesota Avenue and Benning Road

 

  • Final Pavement