Sunday, October 21, 2018 – Saturday, October 27, 2018: Project Update & Photos

Water infratration of westside sidewalk along Minnesota Ave in front of Park 7 apartment.

Installed granite curb and concrete placement for PC gutter west side of Minnesota Ave

Backfilled and compacted for the asphalt electrical PVC conduit duct bank @ station 153+00, the metro entrance, Minnesota Ave NE.

The contractor did the following work: Continued excavating & placing sand based structural soil within the tree space and sidewalk in front of Park 7 apartment and install permeable paver sidewalk; continued working on LID structures in front of DOES building; installed granite curb and PCC gutter along west side of Minnesota Ave in front of DOES building; continued excavating & installing and then backfilling electrical PVC conduit duct bank along Minnesota Ave between Hayes St, NE and Hunt Pl, NE.; installed storm drain connecting pipe for manhole at the north end of the Metro Parking lot entrance; excavated and installed storm drain catch basin at Hayes St; roadway restoration with patching of pothole and trench cut; pavement lane marking on Minnesota Ave between Grant St & Hayes Pl.

Washington Gas (DCI) crew on site to continue excavation of continued working on the relocation and test pit of the twelve inch gas main on the west side of Minnesota Ave

Sunday, October 15, 2018 – Saturday, October 20, 2018: Project Update & Photos

Ongoing work on sidewalk & planters in front of Park 7 apartments.

Ongoing LID work in front of DOES building Minnesota Ave

Backfill of streetlight lateral Minnesota Ave.

The contractor did the following work: Continued excavating & placing sand based structural soil within the tree space and sidewalk in front of Park 7 apartment and install permeable paver sidewalk; continued working on LID structures in front of DOES building;; continued excavating & installing electrical PVC conduit duct bank along Minnesota Ave between Hayes St, NE and Hunt Pl, NE.; roadway restoration with patching of pothole and trench cut; pavement lane marking on Minnesota Ave between Grant St & Hayes Pl.

Washington Gas (DCI) crew on site to continue excavation of Washington Gas line in the north bound lane of Minnesota Ave

Sunday, October 7, 2018 – Saturday, October 13, 2018: Project Update & Photos

Compact density test on roadway SB median lane in front of Park 7 apartment building.

Backfill of streetlight lateral Minnesota Ave.

Ongoing streetlight conduit work on Hayes St/Minnesota Ave.

The contractor did the following work: Continued installation of roadway aggregate base material on Minnesota Ave southbound curb and median lanes north of Benning Rd; continued excavating & placing sand based structural soil within the tree space and sidewalk in front of Park 7 apartment; placed concrete for the brick paver edge restraint in front of Park 7 building ; continued working on LID structures between Benning Rd, NE and DOES access driveway; installed & backfilled 18” PCC pipe at Minnesota Ave/ DOES parking garage entrance; continued excavating & installing electrical PVC conduit duct bank along Minnesota Ave between Grant St, NE and Gault Pl, NE; started excavating for basin connect pipe on Grant St, NE; excavation for BIO-06 (bioretention structure) on north side of Benning Rd by 7-11 store; roadway restoration with patching of pothole and trench cut.

Washington Gas (DCI) crew on site to continue excavation of Washington Gas line in the north bound lane of Minnesota Ave between Sta. 127+50 to 128+00 and crew on site working at the south side of Benning Rd and the north bound lane near the intersection.