TWO-WEEK LOOK AHEAD

10/15/2018 – 10/21/2018

  • Excavate platers, Install under drain pipe, stone and geo fabric, water proofing, planter material, structural soil and pavers
  • Install curb and gutter on west side of Minnesota Ave
  • Continue electrical PVC Conduit duct bank work Phase 2, 4, and 5
  • House water connection east side of Minnesota Ave northbound
  • Catch basin connection

10/7/2018 – 10/14/2018

  • Install under drain pipe, stone and geo fabric, water proofing, planter material and structural soil
  • Install asphalt base at right southbound lane of Minnesota Ave north of Benning Road
  • Install curb and gutter on west side of Minnesota Ave
  • Continue electrical PVC Conduit duct bank work Phase 2, 4, and 5
  • House water connection east side of Minnesota Ave northbound
  • Catch basin connection

9/23/2018 – 10/6/2018

  • Install under drain pipe, stone and geo fabric, water proofing, planter material and structural soil
  • Install asphalt base at right southbound lane of Minnesota Ave north of Benning Rd
  • Install curb and gutter on west side of Minnesota Ave
  • Continue electrical PVC Conduit duct bank work Phase 2,4,5
  • House water connection east side of Minnesota Ave northbound
  • Catch basin connection